Featured Projects

John C. Lincoln: North Mountain – Central Plant Utility Upgrades

Complete Central Plant

Design Assist and Construction

LOCATION OF PROJECT: Phoenix, Arizona
START DATE: October 2011
COMPLETION DATE: September 2012
OWNER: John C. Lincoln Health Network
CONTRACT WITH: Gilbane Building Company
ARCHITECT: OWP Architects
ENGINEER: LSW Engineers
ORIGINAL DD BUDGET: $ 5,400,000
FINAL CD CONTRACT: $ 5,300,000

Description of Project

John C. Lincoln Health Network’s original North Mountain Campus was built in the early 1970’s and included a mechanical plant located in the basement of the hospital. W.D. Manor was selected to provide design assist services to relocate and expand the central plant from its existing location, to a new state of the art, low KW per ton, alternate location adjacent to the existing patient tower. The hospital’s primary objective was to never interrupt the existing central plants ability to provide cooling for the hospital.

The project included temporary cooling towers to allow the new plant to be built on the existing tower yard.  The 3000 ton temporary tower plant was a vital component of the project and provided temporary condenser water for over 12 months. The new plant consists of N+1, 2,700 tons of chilled water cooling through a primary, secondary piping arrangements, stainless steel cooling towers, an N+1 500 Hp steam boiler system, underground chilled water piping, and a new energy management and control system.

The new plant was commissioned before connection to the existing hospital, and within a 2 hour period, the old antiquated plant was disconnected and the new plant took over the building load.  W.D. Manor, along with our partner subcontractors, performed the entire piping installation in less than 5 months, a task unheard of in the HVAC industry.

Mission Statement

W. D. Manor is committed to uncompromised quality and service. We provide the best possible mechanical contractor products, services and leadership. We emphasize teamwork, unparalleled training and development of our employees with continuous improvement in everything we do.

Need Support Now?

W.D. Manor provides Client Support:

  • 24 hours a day
  • 7 days a week
  • 365 days a year

Call now: (602) 253-0703

Contact W.D. Manor

Address:
1838 North 23rd Avenue Phx, AZ 85009
Phone: (602) 253-0703

Hours:
Monday - Friday 8am–6pm

Contact Us